What we form

Footings and pads
Strip footings, pad footings, grade beams and pile caps.
Walls
Foundation walls, retaining walls, shear walls and elevator cores.
Columns
Square, rectangular and round, to exposed or covered finish.
Suspended slabs
Flat slabs, slab bands and slabs on steel deck.
Slabs on grade
Warehouse floors, parking levels and equipment pads.
Site concrete
Curbs, ramps, stairs, loading docks and aprons.

The cycle for a suspended slab

Every floor repeats the same seven steps. The speed of a structure is the speed of this cycle.

The cycle for a suspended slabSeven steps repeated on every floor: form, reinforce, review, pour, cure, strip and reshore.1FormDeck and shoringset to elevation2ReinforceBars, chairs,sleeves, embeds3ReviewEngineer checks thesteel before the pour4PourPlace, consolidate,finish5CureProtect the slab,test the cylinders6StripForms come off at thespecified strength7ReshorePosts carry the slabuntil it can carry itselfBefore the pourAfter the pour

It starts with layout

Footings are set out from the surveyor’s gridlines and checked before the pour, because everything above is built from them.

Elevations are set with a laser level. Reinforcing and dowels are placed to the drawings, and the bottom of the excavation is reviewed before concrete is ordered.

A wall that starts in the right place and at the right height does not have to be corrected by the trades that follow.

Two workers tying reinforcing steel in footing forms at the bottom of an excavation
Footing forms and reinforcing at the bottom of the excavation

Strength and temperature

Two things decide when a form can come off and when the next floor can go on: how fast the concrete gains strength, and how cold it is.

Strength gain

Typical gain for a normal Portland cement mix cured at 20 °C. Most of the strength arrives in the first two weeks.

How concrete gains strengthCurve of typical compressive strength against time: 40 percent of design strength at 3 days, 65 percent at 7 days, 90 percent at 14 days and design strength at 28 days.0%25%50%75%100%037142128Days after the pourShare of 28-day design strength40%at 3 days65%at 7 days90%at 14 daysdesign strength

Cold weather

Below the 5 °C line, concrete has to be heated and protected or it will not reach its strength.

Cold-weather concrete thresholdsThermometer marking 5 degrees Celsius, at or below which cold-weather measures begin, and 10 degrees, the minimum concrete temperature for 72 hours after placing.-20°-10°0°10°20°30°Concrete kept at 10 °C or warmerfor at least 72 hours after placingAir at or below 5 °CCold-weather measures begin:heated enclosures, insulatedblankets, heated mix water

Stripping and loading times on a project are set by the engineer and confirmed by test cylinders.

What the finished wall shows

Concrete records the form it was cast in. Panel joints, tie spacing, the tightness of the form and the way the concrete was vibrated are all visible once the forms come off.

Where concrete will stay exposed, the panel layout and the tie pattern are drawn and agreed before the forms are built. Where it will be covered, the tolerances that matter are plumb, line and elevation.

A worker patching tie holes on a stripped concrete wall
Tie holes being patched on a stripped wall

Forming questions

Do you supply the concrete, the reinforcing and the pump?

We price forming on its own or as a complete package with reinforcing, concrete supply, pumping, placing and finishing. The bid states which.

Do you pour in winter?

Yes. Cold-weather work is planned with heated enclosures, insulated blankets and heated concrete, and the cost of protection is shown in the price.

Who designs the formwork and shoring?

Formwork and shoring that need engineering are designed and stamped by a professional engineer, and the drawings are on site before the forms are built.

Do you form residential foundations?

Yes. We form footings, foundation walls and structural slabs for custom homes and multi-unit residential buildings.

Have structural drawings to price?

Send the drawings, the specifications and the date you need a price.