Before construction starts in Ontario
The filings, surveys and plans that have to be in place in the first week of a job, and who is responsible for each.
Updated
Short answer
Before work starts on an Ontario project, the constructor files a Notice of Project with the Ministry of Labour where labour and materials are expected to exceed $50,000. Underground services are located through Ontario One Call, the owner’s list of designated substances is in every bidder’s hands, the building or demolition permit is issued, and a site-specific safety plan names the supervisor.
The checklist
| Item | Who | When | Rule |
|---|---|---|---|
| Notice of Project | Constructor | Before work starts | Where labour and materials are expected to exceed $50,000 (O. Reg. 213/91) |
| Designated substances list | Owner, to every bidder | Before a contract is made | Occupational Health and Safety Act, section 30 |
| Locates | Whoever is digging | Before any excavation | Requested through Ontario One Call |
| Building or demolition permit | Owner, or an agent the owner authorizes | Before the work it covers | Building Code Act, section 8 |
| Site-specific safety plan | Constructor | Before work starts | Hazards, controls, emergency procedures and the supervisor |
| Engineer’s reviews | Owner’s engineer, booked by the constructor | At the hold points on the drawings | Excavation, formwork, shoring and reinforcing |
| Construction hours | Constructor | Every working day | The municipal noise by-law |
| Payment terms | Owner and contractor | In the contract | Construction Act: 28 days, 7 days, 10% holdback |
What the owner provides
- Designated substances list
- Asbestos, lead, silica and the other designated substances on the site, before bidding.
- Drawings and specifications
- Issued for construction, with every addendum.
- Survey and geotechnical report
- Where the work depends on them.
- Approvals the owner holds
- Site plan approval and the building permit, unless the contract gives them to the contractor.
- Access and utilities
- Who provides site access, power and water.
- Insurance
- Builder’s risk and liability, as the contract sets out.
What the contractor provides
- Constructor’s duties
- Under the Occupational Health and Safety Act, for the whole site.
- Supervisor
- A competent supervisor named for the site.
- Schedule
- The pours, the hold points and the trades that follow.
- Insurance and clearances
- Certificates as the contract requires, including the workplace safety clearance.
- Submittals
- Shop drawings, mix designs and product data, for review.
- Site set-up
- Fencing, hoarding, signage, washrooms and erosion control.
Questions
Who is the constructor on a project?
The person who undertakes the project for the owner, usually the general contractor. An owner who hires more than one contractor directly can become the constructor and take on its duties.
Is a Notice of Project needed for a renovation?
Yes, where the total cost of labour and materials is expected to exceed $50,000, whether the work is new construction, renovation or demolition.
What is a designated substance?
One of the eleven substances regulated under the Occupational Health and Safety Act, including asbestos, lead, mercury and silica. The owner identifies those present on the site and lists them for bidders before a contract is made.
Sources
- Government of Ontario, File a Notice of Project
- Occupational Health and Safety Act, R.S.O. 1990, c. O.1, section 30
- Ontario Regulation 213/91, Construction Projects
- Building Code Act, 1992, S.O. 1992, c. 23
- Ontario One Call
- Construction Act, R.S.O. 1990, c. C.30
Checked against these sources on . This page is general information about building in Ontario. It is not legal advice, and the rules change, so confirm the current requirement for your project.