Before construction starts in Ontario

The filings, surveys and plans that have to be in place in the first week of a job, and who is responsible for each.

Updated

Short answer

Before work starts on an Ontario project, the constructor files a Notice of Project with the Ministry of Labour where labour and materials are expected to exceed $50,000. Underground services are located through Ontario One Call, the owner’s list of designated substances is in every bidder’s hands, the building or demolition permit is issued, and a site-specific safety plan names the supervisor.

The checklist

ItemWhoWhenRule
Notice of ProjectConstructorBefore work startsWhere labour and materials are expected to exceed $50,000 (O. Reg. 213/91)
Designated substances listOwner, to every bidderBefore a contract is madeOccupational Health and Safety Act, section 30
LocatesWhoever is diggingBefore any excavationRequested through Ontario One Call
Building or demolition permitOwner, or an agent the owner authorizesBefore the work it coversBuilding Code Act, section 8
Site-specific safety planConstructorBefore work startsHazards, controls, emergency procedures and the supervisor
Engineer’s reviewsOwner’s engineer, booked by the constructorAt the hold points on the drawingsExcavation, formwork, shoring and reinforcing
Construction hoursConstructorEvery working dayThe municipal noise by-law
Payment termsOwner and contractorIn the contractConstruction Act: 28 days, 7 days, 10% holdback

What the owner provides

Designated substances list
Asbestos, lead, silica and the other designated substances on the site, before bidding.
Drawings and specifications
Issued for construction, with every addendum.
Survey and geotechnical report
Where the work depends on them.
Approvals the owner holds
Site plan approval and the building permit, unless the contract gives them to the contractor.
Access and utilities
Who provides site access, power and water.
Insurance
Builder’s risk and liability, as the contract sets out.

What the contractor provides

Constructor’s duties
Under the Occupational Health and Safety Act, for the whole site.
Supervisor
A competent supervisor named for the site.
Schedule
The pours, the hold points and the trades that follow.
Insurance and clearances
Certificates as the contract requires, including the workplace safety clearance.
Submittals
Shop drawings, mix designs and product data, for review.
Site set-up
Fencing, hoarding, signage, washrooms and erosion control.

Questions

Who is the constructor on a project?

The person who undertakes the project for the owner, usually the general contractor. An owner who hires more than one contractor directly can become the constructor and take on its duties.

Is a Notice of Project needed for a renovation?

Yes, where the total cost of labour and materials is expected to exceed $50,000, whether the work is new construction, renovation or demolition.

What is a designated substance?

One of the eleven substances regulated under the Occupational Health and Safety Act, including asbestos, lead, mercury and silica. The owner identifies those present on the site and lists them for bidders before a contract is made.

Sources

  1. Government of Ontario, File a Notice of Project
  2. Occupational Health and Safety Act, R.S.O. 1990, c. O.1, section 30
  3. Ontario Regulation 213/91, Construction Projects
  4. Building Code Act, 1992, S.O. 1992, c. 23
  5. Ontario One Call
  6. Construction Act, R.S.O. 1990, c. C.30

Checked against these sources on . This page is general information about building in Ontario. It is not legal advice, and the rules change, so confirm the current requirement for your project.

Tell us about the project.

Design-build briefs, tender invitations, budget requests and site walk-throughs. Tell us the scope, the location and the timing.